Outages Imminent in Lagos as Ikeja Electric Announces 132KV Lines Upgrade

Major Power outages are imminent at Lagos State Secretariat, The Lagos State University Teaching Hospital (General Hospital), The Ikeja High Court, and The Ikeja Mall (Shoprite), among others.

 

Nigeria’s largest Electricity Distribution company, Ikeja Electric (IE), has announced the planned re-conductoring of 132KV lines embarked upon by the Transmission Company of Nigeria (TCN), aimed at expanding the capacity to wheel more power.

Platforms Africa reports that the Chief Technical Officer, Ikeja Electric (IE), Jide Kumapayi, who disclosed this while addressing journalists, said the upgrade by the TCN couldn’t have come at a better time as the capacity of most of the 132KV lines become limited due to time and usage culminating to inability to operate at full capacity.

According to Kumapayi, the TCN is currently embarking on the upgrade of 132 KV lines from Ikeja West to Ota and this activity is phased into four stages. This is the second stage and TCN is upgrading the 132kv lines with more robust and sophisticated replacements which provide an opportunity to increase power evacuation for improved supply to customers as well as offering excellent conductor capacity which can withstand very high voltage.

READ ALSO: Pandora papers: Financial Secrets of World’s Rich, Powerful Exposed in Biggest ever Leak of Offshore Data

Nigeria President Buhari Fires Power Minister, Mamman, over ‘inefficiency’

Meet Abubakar D. Aliyu, new Minister of Power, 3rd in Buhari’s 6-Year Govt

Ikeja Electric deepens CSR investment with DashMe Foundation charity deals

“The upgrade which is set to commence on Monday, October 11, 2021, will affect customers within Oregun, Anifowoshe, Ojodu, Magodo, Omole, Oba-Akran, Oke-Ira, Ogba, Omole Phase 1 and parts of Ikeja, between the hours of 8:00am and 6:00pm daily, for eight weeks , he said.

Major installations that would be affected by the imminent outages, checks by Platforms Africa showed, include the Lagos State Secretariat, The Lagos State University Teaching Hospital (General Hospital), The Ikeja High Court, and The Ikeja Mall (Shoprite).

Others are the Ikeja GRA, Omole Estate and the Magodo Estate.

Kumapayi also noted that IE Technicians will be on standby to provide support wherever technical interventions are required for the duration of the upgrade, especially between the hours of 6pm and 8am when supply will be available to customers.

“Even though this is a TCN project, we owe our customers the duty to inform them of the situation because we interface with them on a daily basis. We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our Network to improve power supply to customers under our network. So we want to appeal to our customers to bear with us as this exercise will be beneficial toward the improvement of power supply in our network” he said.

He reiterated the company’s commitment to improve infrastructure and exceptional service to its esteemed customers, noting the company’s investment in facility upgrade and installations across its six Business Unit as part of its mission of providing quality and reliable services to customers.

Related posts

Leave a Comment